Please be advised that MBQ has recently started the preliminary engineering work required to design future watermain phasing.  First Nations Engineering Services survey crew will be at various locations throughout the community for the next 4-6 weeks completing the topographical survey required to design the watermain servicing. In addition to the field survey, there will be a geotechnical firm conducting borehole drilling throughout the community at various locations for the next 4-6 weeks. To finalize the preliminary engineering FNES may need to access residential properties at times to document homes, driveways and other features. There is no need to enter homes at this time. This work started November 23 and will continue well into December. We do apologize for any inconvenience. If you have any concerns regarding the survey work, please contact Peter Brant or Todd Kring at the Band Office, 613-396-3424 ext: 109. Thank you for your continued patience.

Tyendinaga Mohawk Council and MBQ Community Infrastructure Department